The purpose of this activity is to review the results of Phase 1 with Information Resource Management, Data Resource Management, Systems Resource Management, and Enterprise Resource Management. The review is used to determine whether the project should continued as proposed, revised or discontinued.
OVERVIEW
During Phase 1, Activity G, Project Management conducts a
phase review meeting to obtain the formal project decision from
management. Data Engineering is in attendance to answer any
pertinent questions as they arise.
THIS REVIEW IS EXTREMELY IMPORTANT. Management support and
involvement is essential for project success. A well prepared
concise report gives management the confidence necessary to make
the appropriate project decisions. When executed as described,
Phase 1 eliminates many problems due to oversights and poor
planning. It allows many factors to be considered early enough
to make resolutions that would be expensive and difficult to
make in the later phases. More importantly, unjustified
projects are discontinued before unnecessary expense is
incurred.
Because of the importance of this review, Project
Management and Data Engineering should be extremely well
prepared. Visual aids should be used to explain and clarify
findings. Those in attendance should have the authority to make
decisions.
Copies of the Phase 1 "Data Base Study & Evaluation Report"
should be distributed to pertinent managers well in advance of
the review meeting. This allows the manager ample time to study
the report and prepare for the meeting.
The intent of the review meeting is not necessarily to
explain each section of the report, but to answer questions and
summarize the conclusions. The report, thereby, is the focal
point of the meeting.
There are three possible outcomes from the review meeting:
PROJECT APPROVED
Project Management advises all meeting attendees of the
results of the meeting by memo or letter. The project continues
according to plan.
PROJECT DISAPPROVED
Project Management discontinues all activity on the
project and prepares an audit report as indicated in Phase 6.
This will document the disposition of the project. All study
material is filed in a project file in the Technical Library for
future reference.
REVISE PROJECT
During the review meeting, decisions or discussions may
have indicated a project change or revision. Data Engineering
and Project Management modifies the report as required and
establishes another review meeting (if necessary) to consider
the revised report.
A final and approved copy of the Phase 1 "Data Base
Study & Evaluation Report," with the initials or signatures
of management, is sent to the Technical Library for filing
in the project file.
STEPS IN EXECUTION
|