BUSINESS PURPOSE
The purpose of this activity is to prepare a Detail
estimate and schedule for the activities in Phase 2.
OVERVIEW
When preparing the Phase 2 Detail estimate and schedule,
Enterprise Engineering should consult the Order-of-Magnitude
(O-O-M) estimate and schedule as prepared in Phase 1. The O-O-M
is recorded on the "Project Estimate/Schedule Recap" in the "EEM
Project Plan," which is maintained in the Technical Library. It
lists the anticipated time, cost and schedule for each phase in
the project, including Phase 2.
STEPS IN EXECUTION
- Enterprise Engineering obtains a copy of the Phase 1
"Project Estimate/Schedule Recap" from the Technical
Library.
- Enterprise Engineering prepares a Detail estimate and
schedule for the activities of Phase 2 which is reviewed
with Project Management. The estimate may be either
accepted, rejected or modified.
- Enterprise Engineering returns the "Project
Estimate/Schedule Recap" to the Technical Library for filing.