The purpose of this activity is to review the results of Phase 1 with Executive Management, User Management, Information Resource Management, Systems Resource Management, Data Resource Management, and Enterprise Resource Management. The review is used to determine whether the project should continued as proposed, revised or discontinued.
OVERVIEW
During Phase 1, Activity H, Project Management conducts a
phase review meeting to obtain the formal project decision from
management. Systems Engineering is in attendance to answer
any pertinent questions as they arise.
THIS REVIEW IS EXTREMELY IMPORTANT. Management
support and involvement is essential for project success. A
well prepared concise report gives management the confidence
necessary to make the appropriate project decisions. When
executed as described, Phase 1 eliminates many problems due to
oversights and poor planning. It allows many factors to be
considered early enough to make resolutions that would be
expensive and difficult to make in the later phases. More
importantly, unjustified projects are discontinued before
unnecessary expense is incurred.
Because of the importance of this review, Project
Management and Systems Engineering should be extremely well
prepared. Visual aids should be used to explain and clarify
findings. Those in attendance should have the authority to make
decisions.
Copies of the Phase 1 "System Study & Evaluation Report"
should be distributed to pertinent managers well in advance of
the review meeting. This allows the manager ample time to study
the report and prepare for the meeting.
The intent of the review meeting is not necessarily to
explain each section of the report, but to answer questions and
summarize the conclusions. The report, thereby, is the focal
point of the meeting.
There are three possible outcomes from the review meeting:
PROJECT APPROVED
Systems Engineering advises all meeting attendees of the
results of the meeting by memo or letter. The project continues
according to plan.
PROJECT DISAPPROVED
Systems Engineering discontinues all activity on the
project and prepares an audit report as indicated in Phase 9.
This will document the disposition of the project. All study
material is filed in a project file in the Technical Library for
future reference.
REVISE PROJECT
During the review meeting, decisions or discussions may
have indicated a project change or revision. Systems
Engineering reviews the project and estimates, modifies the
report and establishes another review meeting (if necessary)
to consider the revised report.
A final and approved copy of the Phase 1 "System Study &
Evaluation Report," with the initials or signatures of
management, is sent to the Technical Library for filing in the
project file.
STEPS IN EXECUTION
|