The purpose of this phase is to evaluate the system and project in terms of how well they were delivered as compared to what was proposed in the early phases of the methodology. Several events occur during this phase:
METHODOLOGY NAVIGATION
This represents the concluding phase of the ISEM project. It
is performed either after Phase 8, or if a project has been
discontinued earlier on (such as after Phase 1, 2 or 3).
The formal deliverables resulting from Phase 9 will be
the "System Evaluation Report" which is reviewed by Quality
Assurance prior to being issued to management.
GENERAL DISCUSSION
During Phases 1, 2 and 3, Systems Engineering prepared the
"System Study and Evaluation Report," "System Design Manual" and
"Sub-System Design Manuals." On the basis of these reports,
management either approved or disapproved the project for
design and implementation of the system.
If the project was disapproved, the reasons are outlined
during this phase and placed with the original documentation for
future reference. If the project was approved, this approval
was given as a result of certain expectations outlined within
the reports. The purpose of this evaluation is to determine
if these expectations were realized.
THE BENEFITS OF PHASE 9
"Unless we learn from history, we are doomed to repeat it."
This may be an old adage, but it is certainly true. Many
organizations tend to regard project reviews as a waste of
precious time and resources. Consequently, systems are
installed without any type of follow-up. Because of this, many
of the benefits were never realized. For example, clerical
savings may have been part of the justification for a new
system, but operating management did not reduce or reallocate
the staff to realize the benefits. Without follow-up,
"Parkinson's Law" may occur where "work expands to fill the
time available."
As another example, a new operating management, created
as a result of organizational changes, may not be utilizing the
information provided by the system. They may be unaware of, or
lack knowledge about the system. In order for management to
have confidence in their systems organization and the systems
installed, they should have tangible evidence that their
significant investments are producing the promised results.
The systems organization can realize many benefits from an
"ISEM Evaluation." It is not just a platitudinous statement to
say that "we learn from our mistakes." It is a clear and
established fact. A detailed audit provides Systems Engineering
and Software Engineering with an opportunity to review their
estimating and design skills. This knowledge, along with
historical data, can be gainfully applied to new systems and
projects. As such, estimating guidelines can be updated.
A carefully executed audit can also add to the credibility
of the systems organization by showing how well they performed
and that they can account for their actions.
Finally, as a result of an audit, the systems organization
may find that the new system is simply not functioning in spite
of systems maintenance and revisions. In this event, the audit
may indicate an entirely new approach should be taken as opposed
to continually fighting the problem.
"WHEN" SHOULD YOU CONDUCT PHASE 9?
The System Audit should be scheduled for execution
after the system has operated for an adequate period of time.
Typically, this will be between thirty (30) and ninety (90)
days after Phase 8. In some instances, it may be necessary
to conduct more than one audit, depending on the timing of
implementation and execution of the various sub-systems within
the system. For example, User Management may want a detailed
accounting of project costs immediately after each Phase 8.
The actual system evaluation can follow thereafter.
"HOW" SHOULD YOU PERFORM PHASE 9?
Ideally, the audit should not be performed by the same
individual(s) who developed the system. A neutral third party
should be involved who can audit the system and project
objectively.
The steps required to execute the phase are similar to
those in Phase 1, Activities B and G.
For additional information on these activities:
AUDIT CONSIDERATIONS
During the system audit the Systems Engineer may identify
errors, omissions and severe weaknesses in the new system. In
this event, the Systems Engineer may initiate a Work
Request/Objective to document the modification/improvement. This
will then go through the normal process of evaluation and
priority calculation as provided for under the Enterprise
Engineering Methodology (EEM).
A Project Management (PM) system can assemble all pertinent
project data for analysis. This data can also be exported to
other financial packages and spreadsheets for further analysis
as required.
In addition to controlling information resources, the IRM
provides auditors with the "roadmap" for locating the control
points in a system. Further, the "impact analysis" feature is
useful for considering enhancements.
PHASE 9 DELIVERABLES
The formal deliverable resulting from Phase 9 is the
"System Evaluation Report" which details the findings of the
System Audit. This is then reviewed with management.
DESCRIPTION OF PHASE ACTIVITIES
Activity A - Perform System Audit
Systems Engineering reviews the original system design
documentation to become familiar with how the system was
intended to operate. Next, a survey of the system is
conducted to identify how the system is actually operating.
Any differences are identified and noted as part of the
survey. If any problem areas are identified, Systems
Engineering works with the Users to determine the problem
and possible solutions. If necessary, a Work Request/
Objective is initiated to resolve the issue.
Activity B - Prepare System Evaluation
Project Management prepares the formal Phase 9
"System Evaluation Report" consisting of:
Quality Assurance checks this report to assure conformance
with standards. User Management is then provided a copy of
the report for review, along with
Information/Systems/Data/Enterprise Resource Management.
|