PROJECT SCHEDULING

PLANNING   ESTIMATING   REPORTING   CONTROL
SUPPORT   FORMS

TRANSLATE THIS PAGE TO... Chinese (simple)   Japanese       Dutch   French     German     Italian    
Free Translation courtesy of ALS      Chinese (traditional)   Korean       Portuguese       Russian       Spanish         

CONTENTS

"Time lost is time lost forever; You cannot buy it back."
- Bryce's Law

This section contains the following:

Copyright © 1971-2006 by M. Bryce & Associates
Palm Harbor, Florida, USA
All rights reserved.


 
    INTRODUCTION

    Scheduling is a distinctly separate activity from estimating even though it depends upon accurate estimates. It is the process of converting direct hour estimates into date schedules. Scheduling includes the assignment of resources to tasks in the correct sequence to meet the objectives of the project. This is a complex process and one that is almost impossible without automation. In most organizations, there are many projects, resources and environmental conditions that can influence projects and cause the need for changes in schedules.

    Scheduling is an iterative process of balancing the resources available against the time requirements established for the project. There are several variables involved:

    • The direct hour estimate, either O-O-M or detail.

    • The methodology for the project, as defined by the key events of the project.

    • The human resources to be used on the project, with their effectiveness rate, current schedule, and skills and proficiencies.

    • Project priorities as established by executive management.

    • A corporate calendar which notes weekends, holidays, shutdowns, etc.

    As an example of how a schedule is calculated, assume that there is a professional working on an assignment with an estimate of 100 direct hours. If the individual's planned effectiveness rate is 70%, then the 100 hour estimate converts to a projected 142.85 elapsed hours required to complete the assignment. The elapsed hours in the normal business day is divided into the 142.85 and (using 8 hour work days) results in 17.85 business days required to complete the assignment. These 17.85 business days are applied to the corporate calendar which expresses weekends and holidays, also other commitments for the professional, such as vacations and other work assignments. Taking these into account, start and end dates are then determined.

    If the end date is unsatisfactory to the manager, there are several possible alternatives which can be used to improve the schedule:

    • Reduce the employee's indirect activities and increase their effectiveness rate.

    • Schedule work on weekends and/or holidays.

    • Add additional personnel or use alternative personnel.

    • Increase the number of available hours in the business day (within reason of course).

    • Or combinations of the above.

    By understanding and adjusting the variables associated with a project, a project manager has the ability to play "what if" with a high degree of certainty.

    Scheduling is an activity that is greatly influenced by the concept of effectiveness rate. By examining the use of time, both direct and indirect, realistic schedules can be prepared. The "man hour" approach mentioned earlier does not take the environmental influences into consideration and assumes an effectiveness rate of 100%. Under this approach, the sample schedule would be completed in 12.5 business days as opposed to the 17.85 days mentioned. The difference is that effectiveness rate builds reality into the schedule. It does not make use of some esoteric "fudge factor" as typically used in relation to "man hours."

   

    Time lost, is time lost forever. You cannot buy it back. Because of this, we must carefully manage the use of resources throughout the methodology of the project. The methodology defines the project network which may involve parallel and sequential work. The longest path in the methodology which is critical to the timely completion of a project is referred to as the "critical path." A project will always have a critical path until it is completed or closed. The path will not always be constant; it may vary depending on accomplishments. As one part of a project is concluded, the critical path may change to another branch of the project. Defining and monitoring the critical path is an essential part of project management, not only in scheduling, but in planning and control also.  

    GANTT CHARTS

    One tool that has always been useful for scheduling is the Gantt Chart, which was developed by Henry L. Gantt. It is used for resource allocation and project scheduling. Other names for the Gantt Chart include: planning chart, bar chart, milestone chart, histogram.

    The Gantt Chart is used to plot project schedules as well as human resource allocations; to illustrate:

   
     

    EXAMPLES

    Samples of schedules are included throughout the "PRIDE" methodologies and are expressed on the various Project Control Sheets and Project Estimate/Schedule Recaps. Consult the Examples sub-sections under the various activities. The Gantt Chart and other forms (the "Project Control Sheet" to prepare schedules for Detail estimates (also see alternate form), and; the "Project Estimate/Schedule Recap" worksheet for O-O-M estimates) can be obtained in the "PRIDE" Forms section.

   