PRIDE ® -PM
Project Management
An integral part of Information Resource Management (IRM)

PLANNING   ESTIMATING   SCHEDULING   REPORTING   CONTROL
SUPPORT   FORMS

TRANSLATE THIS PAGE TO... Chinese (simple)   Japanese       Dutch   French     German     Italian    
Free Translation courtesy of ALS      Chinese (traditional)   Korean       Portuguese       Russian       Spanish         

CONTENTS

"Manage from the bottom-up, not just from the top-down; this creates personal commitment and accountability."
- Bryce's Law

This section contains the following:


 
    BACKGROUND

    In 1963, a serious problem developed when the users of a mainframe computer were promised new systems software by the manufacturer. The software included a new multi-processing operating system, new compilers for COBOL and Fortran and supporting utilities including sorts. The promised delivery date for the software had already slipped by almost a year and appeared to be slipping steadily. As a result, the company faced cancellations by their existing customer base, as well as the loss of sales to new customers. Something had to be done quickly since the project seemed to be wallowing with no foreseeable end in sight. It should also be pointed out the company and project participants had not worked on any assignment of this magnitude previously.

    The company's director of product planning correctly concluded they were faced with a management problem, not a technical problem. He made a phone call to his home office and directed two of his managers to immediately relocate themselves and their families to the project site, which happened to be across the country, for an assignment of unknown duration. One of the managers was responsible for all administration and the other for systems programming. The call came on Friday and the managers were to start work the next Monday.

    On the day they arrived, the two managers met with the product planning director and location management. They all agreed some course of action had to be taken to change the environment in order to gain control over the project and deliver the software. The systems and programming manager was assigned the task of evaluating the technical status of the software. The other manager was assigned the responsibility of setting up a system to monitor and control the project.

    The managers walked into an environment of complete disorganization. There were over sixty systems programmers working on the project who were loosely divided into groups assigned to the various parts of the software. Some were working on the operating systems, others were assigned to compilers, etc. Each group had a leader giving out rough assignments. The systems programmers seemed to lack any coordination or motivation to get the job done. No schedules or estimates existed. One of the managers observed the programming staff spending considerable time in the coffee shop across the street whenever they pleased. All project meetings were held on an ad hoc basis. All the ingredients for a successful project were missing: Leadership, commitment and accountability.

    The managers quickly developed a course of action to correct these deficiencies. In terms of leadership, the systems programming manager's assignment was to review each part of the project and assign a leader. The project was divided into units of work consistent with the logical design of the software. Precedent relationships were established between the various units. When this was developed, each work unit was divided into the tasks to be performed such as coding, testing, etc. When this was completed, the units were assigned to individual programmers. Each programmer then made an estimate and schedule for completion for his assignment. Estimates were reviewed by everyone for reasonableness until they arrived at consensus and commitment. It was clear to each individual that they were personally responsible for their own estimates and schedules.

    While this was going on, the administrative systems manager established a control room equipped with a magnetic Gantt chart running across the length of the room. The room had a large conference table with chairs. Also, file cabinets were obtained. The administrative manager designed a file folder which looked like a large envelope. Printed on one side was a calendar showing actual and planned dates for the tasks for each unit. On the other side, was space for a description of the work unit and the name of the person responsible for execution. It also contained space to write comments about project status and changes.

    The Gantt chart and envelopes were posted with the data developed by the systems programming manager. A time reporting system was designed for collecting time data by work unit with summaries showing activity by the various parts of the project. The data from the time reporting system was posted weekly to the Gantt chart and file folder. Weekly meetings were held with each team and its members. At these meetings, progress was discussed, problems resolved and any changes to schedules or estimates were made.

    This new environment was in effect for three months during which time the project was successfully completed and the computer company was able to deliver the software to its customers. What the managers had been able to do was create a work environment where the professionals had commitment and accountability and were provided with effective leadership.  

    CONCEPTS & PHILOSOPHIES

    If we lived in a perfect world, there would not be a need for managers. Everyone would know precisely what their assignments were and would successfully accomplish them on time and within budget. However, the reality is we live in an imperfect world. We as human beings make mistakes; we work on multiple assignments concurrently, and require guidance. It must be recognized from the outset that project management does not come free. Nor does it come naturally to people.

    Traditionally, the typical approach to project management has most often been to find a project manager, provide resources, and then give them an assignment with no direction as to how the project will be conducted or controlled. With this approach, the success or failure of the project is dependent on the abilities and experience of the project manager and how well the manager can organize and train the project team, plan the project, estimate, etc. Consequently, there is significant trial and error in the process. This approach usually results in a unique method for the particular project because it reflects the thinking of the project manager. Different managers use different techniques and ideas.

    Another common approach used was the "brute-force approach." Simply stated, "I don't care how you get the job done; just have it completed by (date)." This approach shows a lack of sensitivity to the complexity of project management.

    There is more to project management than maintaining costs and time schedules. It is the process of applying resources to a defined goal and attaining this goal within time and cost objectives. Fundamentally, it is a people oriented function as opposed to an administrative or clerical function. Project management, therefore, is not a tool or technique, but rather a philosophy of management.

    To put it into proper perspective, project management is analogous to the production control function in manufacturing, which is concerned with controlling the orderly assembly of products. This involves monitoring the assembly lines and assuring that materials management delivers the necessary parts to the assembly lines on time and within reasonable cost. Project management is to a methodology, what production control is to an assembly line. Without the assembly line, production control is a useless exercise. Conversely, without a methodology, project management is useless.

    The ultimate test of a methodology is if it can operate independent of project management. The two are not synonymous. Although they work in concert, there are distinct differences. Whereas a methodology dictates what work is required, project management controls the application of work. Just as an assembly line can produce a product without production control, a methodology can produce a product without project management. Therefore, a methodology is independent of project management, but project management is totally dependent upon a methodology.

    A PROJECT REQUIRES A METHODOLOGY

    BUT A METHODOLOGY DOES NOT REQUIRE A PROJECT
     

    PRODUCTION CONTROL ANALOGY

     

    A project is an application of effort towards prescribed objectives through the execution of a defined sequence of events. All projects have a life cycle; a beginning for planning, a middle for execution, and an end for review. Each project has a unique scope, set of objectives and defined sequence of events. These events are defined by a methodology, whether it is to develop enterprise resources (as in EEM), system resources (as in ISEM), or data resources (DBEM). The methodology thereby is the "roadmap" for a project. It provides organization and direction for the project.

    Project managers must recognize that they are in the business of solving problems, not creating problems. They do not wait for things to happen, they make things happen. This "active" versus "reactive" management philosophy distinguishes management from supervision. Whereas management assigns and reviews work to assure that goals are met, supervision is responsible for implementing the assigned work and directing the daily activities of others. Problems arise when there is more time spent on supervision than on managing and actually performing the work. This phenomenon occurs when people are improperly trained and/or when they are not held accountable for their actions.  

    MINI-PROJECT MANAGER CONCEPT

    At the root of the problem is the issue of accountability and commitment. Historically, companies have taken a unidirectional approach to management. Assignments, estimates and schedules are dictated by management with little concern for the opinion of the people who have to perform the work. This typically results in unrealistic estimates and schedules that are seldom achieved. Why? Because the individual human resources were not consulted and made accountable for achieving the goals. Workers may even go so far as to undermine project plans simply because they were not consulted.

    Instead, companies must learn to manage from the bottom-up, not just top-down. We refer to this approach as the "Mini-Project Manager" concept. Under this approach, people are treated like professionals and are expected to act as such in return. It emphasizes less supervision and more personal management by the individual worker. Employees must learn to supervise themselves. Although, management still provides leadership and direction over assignments, employees participate in the estimating, scheduling and control process. This produces far more realistic results which can be more effectively managed. It also creates greater personal commitment to project activities since the individual worker's voice is heard.

    MINI-PROJECT MANAGER CONCEPT

    "Manage from the bottom-up, not just top-down.
    Create personal commitment and accountability."
     

    TIME DEFINITIONS

    The "Mini-Project Manager" concept begins with a different perspective of time. Fundamentally, there are two types of time, available and unavailable. Available time is time used for productive work as in a normal work day. Unavailable time is time that is not available to perform productive work, such as holidays, vacations, shutdowns, etc. Although both available and unavailable are schedulable, we are primarily concerned with the utilization of available time.

    Available time is divided into two categories: direct and indirect time. Direct time is that amount of time expended on productive work, such as following the assigned phases/activities/steps of a methodology. Indirect time is time that does not contribute to productive work, such as non-project related meetings, training, breaks, etc.

    Under the "Mini-Project Manager" concept, direct time is the responsibility of the individual employee to manage. In other words, they are personally responsible for managing their work effort. Conversely, indirect time is the responsibility of management to control the work environment.

    WHAT IS TIME?
    PRINCIPLE: Time is a resource that must be managed like any other resource.

    EFFECTIVENESS RATE = DIRECT ÷ (DIRECT + INDIRECT)  

    EFFECTIVENESS RATE

    This view of time highlights the fact there are interferences, whether planned or unplanned, that prevent workers from expending 100% of the available time on assignments. The relationship of direct to indirect time is called "effectiveness rate" and is expressed as the percent of time spent on direct work. If someone has a low effectiveness rate, this may highlight to the manager that an employee is experiencing too many interferences, such as meetings or breaks. The manager can then exercise authority and minimize or eliminate the indirect activities if it is deemed unproductive or incorrect. In this way, the manager is controlling the work environment. On the other hand, a low effectiveness rate is not always considered undesirable. For example, a manager may send employees to a training class to sharpen their skills and become more productive. The employee's effectiveness rate for this period would be very low.

    As should be apparent, "effectiveness rate" is noticeably different than an efficiency rate. It is simply an expression of the availability of an individual to do the "right" work. A worker can have a high effectiveness rate, yet may be inefficient at their assignments. Conversely, someone with a low effectiveness rate may be the most efficient worker in the company.

    To calculate an individual's effectiveness rate, divide the total direct hours in a day by the total available hours in a day. For example, in an eight hour business day, if the employee spends six hours on direct assignments and two on indirect activities, this means the person is 75% effective for that day. Although effectiveness rates will vary, 60% to 70% is a typical rate. This ratio can apply to an individual, a department, or for an entire organization. Ultimately, the effectiveness rate provides a measure of how well time is being used in the work environment.

    As we will see, this definition of time will have other beneficial uses, particularly in the areas of estimating, scheduling and control. This view is more realistic than the "man hour" concept which assumes a "one-to-one" relationship of the work to elapsed time and is not concerned with the control of indirects. According to the "man hour" approach, a person is 100% effective. When something should be completed is quite different than how much work is involved. For example, it could take three elapsed weeks to accomplish ten hours of direct work. It all depends on how much time is available; what other activities are involved; and what interferences exist.

    The underlying philosophy behind all of this is that time is a resource that must be managed like any other resource. Before we can manage it, we must first understand it.  

    PROJECT MANAGEMENT ACTIVITIES

    There are five basic activities associated with project management; each directly affects the others:

     

    PROJECT MANAGEMENT SYSTEM

    A Project Management system is an information system used to support the basic activities of project management. There are a variety of project management related software packages attacking the subject piecemeal. Some are used to develop project networks, others are used to calculate schedules or estimates, or simply to perform project bookkeeping. However, very few take an integrated approach to project management. This is a serious problem since dependencies exist between project management activities; to illustrate:

    • Planning is the basis for developing estimates, schedules, and for project control.

    • Estimates are used as the basis for key project decisions (approve, reject, revise), and are used to calculate schedules.

    • Scheduling requires a project plan, involving a network and human resources with skills and proficiencies.

    • Reporting requires assignment of tasks, estimates and schedules.

    • Control requires effective planning, estimating, scheduling, and reporting.

    A superficial approach to project management will produce shallow results. Since a project management system is used as a communications vehicle for management, the more people involved in the program, the greater the communications and coordinated use of resources.

    Can the philosophies of project management be adopted and implemented by a single person? Yes. A group of people for a single project? Yes. A department or division? Yes. The entire company? Yes. In fact, as the scope grows, communications improves and the philosophy is more consistently applied.

    REQUIREMENTS FOR A PROJECT MANAGEMENT SYSTEM
    GENERAL

    SUPPORTS ANY TYPE OF PROJECT.
    DISTINGUISHES D/I/U ACTIVITIES.
    PROMOTES MINI-PM CONCEPT.
    INTEGRATED APPROACH.
    IMPORT/EXPORT CAPABILITIES.
    SCHEDULING SUPPORT

    PROVIDES FOR EFFECTIVENESS RATE.
    MULTI-VERSIONING.
    RESOURCE ALLOCATIONS.
    PLANNING SUPPORT

    VARIOUS WBS.
    INTERNAL & EXTERNAL DEPENDENCIES.
    MULTIPLE RESOURCES/MULTIPLE
    PROJECTS/MULTIPLE ASSIGNMENTS.
    SKILLS INVENTORY.
    REPORTING SUPPORT

    RECORDS & VALIDATES TIME.
    ESITMATE TO DO.
    MAINTAINS HISTORY.
    RECORDS OUT-OF-POCKET
      EXPENDITURES.
    ESTIMATING SUPPORT

    DETAIL & O-O-M.
    MULTI-VERSIONING.
    GUIDELINES (EST. GENERATOR)
    CONTROL SUPPORT

    POSTS TIME TO PROJECTS.
    VARIOUS STATUS REPORTS TO
      ANALYZE PROJECTS & RESOURCES.
    BILLING/CHARGEBACK.

    The scope of project management affects many people:

    • The individual worker will prepare estimates and schedules, perform project work, and report on activities.

    • The project manager will plan and direct the use of resources on projects.

    • Department managers will administer resources and control projects within an area.

    • Executive management will establish project priorities and monitor project progress.

    Obviously, project management should not be restricted to a handful of people or projects. Dozens of projects may be active at any one time, involving hundreds of workers, across departmental boundaries. Synchronization of the work effort is required to maximize effect and minimize confusion. Project management, therefore, should be viewed as a corporate philosophy as opposed to a technique used by various people.

    It must be remembered that a project management system is not a substitute for management. It does not make decisions; people do, based on information produced from the system. Once convinced of the action or decision to make, make it. There is little point to any information system if you do not take advantage of the information it provides. What this highlights is the fact that a project management system will only be as effective as the people who use it.  

    PROJECT ADMINISTRATION

    This function should not be confused with Project Management. The primary responsibility for Project Control rests with Project Management. Project Administration is concerned with the collection, recording and maintenance of Project data and, as such, is the chief administrator of the Project Management system. At any one time, many projects may be in progress within the systems department and therefore, coordination is required for the processing of project data. The Project Administrator can be viewed as the administrative aid to both the Project Managers and Departmental Management.

    The Project Administrator is concerned with the following "PRIDE" forms:

    TIME DISTRIBUTION WORKSHEET

    A Time Distribution Worksheet is prepared weekly by each professional involved with direct project activities including systems maintenance. Before instituting the Weekly Time Distribution, all indirect activities should be identified. Generally, any activity not identified in the Phases of "PRIDE", or in Data and Project Management, is an indirect activity. Indirect activities include such things as: meetings, training, employee personal matters, travel, review, etc. Scheduled holidays or vacations should not be used when computing effectiveness since these days are "unavailable" for scheduling and will be identified accordingly in the Planning Charts. A list of the approved indirect activities should be issued to all personnel to use when preparing time sheets.

    It is important for estimating and scheduling purposes to establish the Effectiveness Rate as quickly as possible. The Time Distribution Worksheet provides the ability to separate and identify both direct and indirect hours. As an aside, development organizations are typically 60% - 70% effective.

    Time Reporting data is collected on a weekly cycle. Two decisions should be made in reference to this data collection:

    1. What is the scheduled work week in hours? (e.g., 40 hours)

    2. When does the work week start and end? (e.g., Monday - Friday)

    The Project Administrator collects all Time Distributions at the end of the weekly cycle. They are checked for arithmetic correctness and completeness of hours in terms of the scheduled work week. Lack of discipline concerning the submission and correctness of the time distributions on the part of departmental personnel can create serious delays in processing. The Project Managers are responsible for ensuring this does not become a problem and resolving any problems encountered by the administrator. An automated Project Management system can materially help in validating project/time data.

    After the Weekly Time Distributions have been audited by Project Administration, they are recapped by the administrator by Project, System Structure and Phase Activity numbers for Direct Hours and by type activity for Indirect Hours on to a Time Distribution Worksheet. Using the completed recap, the Effectiveness Rate is computed and entered on the recap. This data should be plotted on a spreadsheet for review and analysis.

    After completing the Effectiveness Rate, the recap is forwarded to departmental management review. Since this rate is used for project planning, any variations can have significant effect on project schedules such as schedule overruns or underruns. Management should investigate the reasons for these variations and take corrective action where necessary.

    PROJECT CONTROL SHEET

    The primary responsibility for the preparation and maintenance of these sheets rests with the person assigned to the phase. A copy is retained by the project manager and Project Administrator.

    After the weekly time sheet has been prepared by the individual, he posts the hours appropriate to each activity. The new hours are added to those previously recorded. The actual fields on the control sheets should be updated in pencil to permit the use of the same control sheet each successive week.

    The Project Manager reviews the control sheet with the analyst involved. Jointly, they establish by review the completion status of the activities being performed. They enter on the Control Sheet the hours to complete and any start or end dates. This review is the most critical in Project Management. At this point, it can be established if the phase and activity are on schedule and within estimated hours. If there are any significant changes required at this juncture, the Project Manager and the individual prepare a new revised Control Sheet outlining on the reverse side the reasons for the revision the new course of action. The Project Manager also will review the effect of this change on the overall project and submit and/or make any appropriate changes. From the updated control sheets, the Project Manager updates the various Project Planning Charts. A copy of the updated overall project planning chart and completed control sheets are returned to the Project Administrator who in turn revises original Control Sheets.

    PLANNING CHART (GANTT CHART)

    Based on the updated project data from the control sheet, the Administrator updates the individual Resource Allocation Charts (also using the Planning Chart form) both as to planned additions, revisions and actual status.

    Since the problem of resource allocation is an overall department problem, it is recommended that the Administrator maintain the individual resource allocations. This is an excellent check on the various Project Managers' execution of Project Management since these allocations cannot be updated without all steps being accomplished.

    GENERAL COMMENTS - PROJECT ADMINISTRATION

    At first blush, it may appear that the Project Administration function involves considerable clerical and Project Management effort. Experience will show that this function saves considerable time that was previously spent both by the Project Manager and others in the establishment and dissemination of project status data. The discipline once established provides an orderly and effective way of managing projects. The important aspect of this control system is that the individual is responsible for his own activities and reporting.

    The foregoing general steps do not cover all the possibilities or actions that should be taken as a result of processing project data. Each week, Project Management and departmental management should review the project data for any conflicts between projects and take any additional steps necessary.

    Again, an integrated and automated Project Management system can greatly simplify the life of a Project Administrator, but it does not eliminate the need for the function. Project Administration is the "Traffic Cop" that monitors all projects in progress and enforces policy in terms of time reporting and when to revise estimates and schedules. In many organizations the Project Administrator and the Technical Librarian are one and the same person.  

    BENEFIT$

    The benefits of project management are numerous:

    • It assures that project personnel are "doing the right things" to satisfy project objectives and plans.

    • It creates personal commitment and accountability.

    • It demystifies the activities of project management, such as estimating and scheduling.

    • Improved control over the organization.

    • Improved communications within the organization.

    • Improved accuracy of estimates and schedules.

    • Improved use of resources.

    • Improved productivity.

    • Improved control over cash flow.
     

    ADDITIONAL REFERENCES

    See the Functional Description section for narratives describing the following Project Management related functions:

    For other subjects related to Project Management, consult:

   


Copyright © 1971-2008 by M. Bryce & Associates
Palm Harbor, Florida, USA
All rights reserved.